Its 11 weeks since we started the actual build process and from site scrape until now so much has happened.
Slab
Frame
First Fix Electrics and Plumbing
Roof Tiled
Windows
Front Door
Bi Fold Doors
Wrap
Bricks
Gyprock
Plastering
Cornices
Stairs
First Floor Bricks
Wet Areas Waterproofed
Doors and ...................
Cabinets
Now you can pause for breath! What is there left to do:
Finish Cabinets
Caeserstone Bench Tops
Sinks
Baths
Showers
Appliances
Architraves
More Doors
Tiling of Floors and Bathrooms
Carpets
Electrics
Air Conditioner
Plumbing
Painting
Concrete
Oh and we have to do the pool, fencing and landscaping.
Feels like we are about a third to almost halfway through now. Initial guesstimate from the SS is that the build would take around 25 weeks, I though he was mad at first now I'm actually thinking he may have been right.
Bets that we move in November anyone?
Wow, your build has caught up to ours now! We had stone benchtops go in this week, then the tilers come back to finish tiling. We may be in by end of October. Like you we've been impressed with the quality of workmanship so far. Also, when something wasn't done properly, the supervisor gets it fixed without any hassles. Very happy.
ReplyDeleteAmazingly Fast!!
ReplyDelete